Project Name Humanities Complex Replacement
CFIS 40.14.114
District EL CAMINO COMMUNITY COLLEGE DISTRICT
College EL CAMINO COLLEGE
City Torrance
County Los Angeles
Senate District 25
Assembly District 51
Project Description and Status
Project Type Expand Instruction
Date Funded 8/24/2007
Project Description This project provides equipment funds for a new 55,099 square foot Humanities Complex. The building will have 16,948 square feet (sf) of lecture, 21,550 sf of laboratory, 9,021 sf of office, 6,985 sf of library and 595 sf of other space. The project includes demolition of an inefficient and undersized instructional facility built in 1950.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 6/1/2004 6/1/2004
Preliminary Planning Approved, Design Begins 11/1/2004 11/1/2004
Design Approved, Authorized to go to Bid 10/1/2005 10/1/2005
Construction Begins 12/1/2005 12/1/2005
Facility Enters Into Use 6/1/2007 6/1/2007
Project Closeout 6/22/2009
Project Budget Summary
State Financing $2,686,000
Local/Non-State Financing $21,666,700
Total Financing $24,352,700
State Contact Hoang Nguyen
hnguyen@cccco.edu
District Contact Robert Gann
3106603015
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $0 $769,000 $769,000
Working Drawings $0 $1,044,000 $1,044,000
Construction $0 $19,853,700 $19,853,700
Equipment $2,686,000 $0 $2,686,000
Total Project Financing $2,686,000 $21,666,700 $24,352,700
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $769,000 $0 $769,000
Working Drawings $1,044,000 $0 $1,044,000
Construction $19,854,000 $0 $19,854,000
Contract $18,779,000 $0 $18,779,000
Allowances $1,075,000 $0 $1,075,000
Equipment $2,686,000 $0 $2,686,000
Total Project Financing $24,353,000 $0 $24,353,000