California Community Colleges Proposition 1D Project Details
Project Name Music Modernization
CFIS 40.11.313
District COAST COMMUNITY COLLEGE DISTRICT
College ORANGE COAST COLLEGE
City Costa Mesa
County Orange
Senate District 35
Assembly District 68
Project Description and Status
Project Type Modernize Instruction
Date Funded 2/20/2009
Project Description The project provides for the reconstruction of two buildings that will total 11,866 ASF. The modernized buildings will provide 8,700 ASF of Lab Space, 752 ASF of office space, 726 ASF of library space, and 1,708 ASF of other music related space.
Project Status Under Construction
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/1/2009 9/2/2009
Preliminary Planning Approved, Design Begins 6/15/2010 6/14/2010
Design Approved, Authorized to go to Bid 5/25/2012 5/1/2012
Construction Begins 8/15/2012 8/1/2012
Facility Enters Into Use 1/1/2014
Project Closeout
Project Budget Summary
State Financing $2,689,000
Local/Non-State Financing $3,032,556
Total Financing $5,721,556
State Contact Jim Rogaski
jrogaski@cccco.edu
District Contact Jerry Marchbank
7144384731
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $185,000 $184,553 $369,553
Working Drawings $158,000 $157,561 $315,561
Construction $2,346,000 $2,345,394 $4,691,394
Equipment $0 $345,048 $345,048
Total Project Financing $2,689,000 $3,032,556 $5,721,556
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $369,000 $105 $369,105
Working Drawings $315,000 $122 $315,122
Construction $6,694,000 $2,003,212 $4,690,788
Contract $6,280,000 $2,023,880 $4,256,120
Allowances $414,000 $20,668 $434,668
Equipment $341,000 $4,048 $345,048
Total Project Financing $7,719,000 $1,998,937 $5,720,063