California Community Colleges Proposition 1D Project Details
Project Name Student Services Building
CFIS 40.09.126
District CITRUS COMMUNITY COLLEGE DISTRICT
College CITRUS COLLEGE
City Glendora
County Los Angeles
Senate District 29
Assembly District 59
Project Description and Status
Project Type Expand Institution
Date Funded 6/30/2006
Project Description The project constructs a new 36,111 square foot Student Services building with of 11,589 square feet (sf) of office, 4,445 sf of library space, and 4,100 sf of other space and locally funded space for a 1,200 sf bookstore, 4,677 sf student recreation area, 1,690 sf health center, and 8,410 sf of event venue space.
Project Status State Accounts Closed
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/1/2006 11/16/2006
Preliminary Planning Approved, Design Begins 2/1/2007 6/8/2007
Design Approved, Authorized to go to Bid 2/1/2008 2/25/2008
Construction Begins 5/14/2008 5/16/2008
Facility Enters Into Use 8/1/2009 10/1/2011
Project Closeout 3/20/2013
Project Budget Summary
State Financing $5,926,000
Local/Non-State Financing $18,792,000
Total Financing $24,718,000
State Contact Jim Rogaski
jrogaski@cccco.edu
District Contact Carol Horton
6269148886
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $270,000 $367,000 $637,000
Working Drawings $123,000 $756,000 $879,000
Construction $5,126,000 $16,634,000 $21,760,000
Equipment $407,000 $1,035,000 $1,442,000
Total Project Financing $5,926,000 $18,792,000 $24,718,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $637,000 $0 $637,000
Working Drawings $879,000 $0 $879,000
Construction $19,771,000 $1,989,000 $21,760,000
Contract $18,773,000 $1,989,000 $20,762,000
Allowances $998,000 $0 $998,000
Equipment $1,442,000 $55 $1,442,055
Total Project Financing $22,729,000 $1,989,055 $24,718,055