California Community Colleges Proposition 1D Project Details
Project Name Health Wellness Center
CFIS 40.06.112
District CABRILLO COMMUNITY COLLEGE DISTRICT
College CABRILLO COLLEGE
City Aptos
County Santa Cruz
Senate District 11
Assembly District 27
Project Description and Status
Project Type Expand Instruction
Date Funded 6/30/2006
Project Description This project constructs a 39,120 square foot project that will house allied health programs, a fitness program, a stroke rehabilitation program and related health and wellness activities. The project includes 3,370 square feet (sf) of lecture, 27,120 sf of labortory, 3,960 sf of office, 800 sf of technology space, and 3,870 sf of other space.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 11/1/2006 11/16/2006
Preliminary Planning Approved, Design Begins 6/1/2007 6/8/2007
Design Approved, Authorized to go to Bid 2/1/2008 2/25/2008
Construction Begins 5/1/2008 5/19/2008
Facility Enters Into Use 5/1/2011 5/1/2010
Project Closeout 8/18/2014
Project Budget Summary
State Financing $11,675,000
Local/Non-State Financing $15,254,238
Total Financing $26,929,238
State Contact Lan Yuan
lyuan@cccco.edu
District Contact Joe Nugent
8314796465
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $91,000 $706,000 $797,000
Working Drawings $151,000 $669,000 $820,000
Construction $10,248,000 $13,819,238 $24,067,238
Equipment $1,185,000 $60,000 $1,245,000
Total Project Financing $11,675,000 $15,254,238 $26,929,238
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $797,000 $0 $797,000
Working Drawings $820,000 $0 $820,000
Construction $20,500,000 $3,567,238 $24,067,238
Contract $19,501,000 $3,404,915 $22,905,915
Allowances $999,000 $162,323 $1,161,323
Equipment $1,245,000 $0 $1,245,000
Total Project Financing $23,362,000 $3,567,238 $26,929,238