California Community Colleges Proposition 1D Project Details
Project Name Wellness Center
CFIS 40.04.105
District BARSTOW COMMUNITY COLLEGE DISTRICT
College BARSTOW COLLEGE
City Barstow
County San Bernardino
Senate District 18
Assembly District 34
Project Description and Status
Project Type Support Instruction
Date Funded 8/24/2007
Project Description The project constructs a 20,309 square foot Wellness Center at Barstow College, comprised of 18,877 square feet (sf) of physical education activity space, 372 sf of office, and 1,060 sf of other space.
Project Status Under Construction
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 8/28/2007 8/29/2007
Preliminary Planning Approved, Design Begins 8/9/2008 8/9/2008
Design Approved, Authorized to go to Bid 2/11/2011 2/1/2011
Construction Begins 5/31/2011 5/31/2011
Facility Enters Into Use 1/30/2015
Project Closeout
Project Budget Summary
State Financing $10,018,000
Local/Non-State Financing $2,448,000
Total Financing $12,466,000
State Contact Cheryl Larry
clarry@cccco.edu
District Contact George Walters
7602522411
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $270,000 $351,000 $621,000
Working Drawings $26,000 $384,000 $410,000
Construction $9,475,000 $1,713,000 $11,188,000
Equipment $247,000 $0 $247,000
Total Project Financing $10,018,000 $2,448,000 $12,466,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $621,000 $25,306 $595,694
Working Drawings $410,000 $11,504 $398,496
Construction $10,508,000 $1,090,746 $11,598,746
Contract $9,914,000 $714,100 $10,628,100
Allowances $594,000 $376,646 $970,646
Equipment $247,000 $4,261 $242,739
Total Project Financing $11,786,000 $1,049,675 $12,835,675