California Community Colleges Proposition 1D Project Details
Project Name Health and Science Building
CFIS 40.03.115
District ANTELOPE VALLEY COMMUNITY COLLEGE DISTRICT
College ANTELOPE VALLEY COLLEGE
City Lancaster
County Los Angeles
Senate District 17
Assembly District 36
Project Description and Status
Project Type Expand Instruction
Date Funded 8/24/2007
Project Description The project constructs a new health and science instructional building of 66,041 assignable square feet (asf) to replace 3 older science buildings built in 1960. The project expands instructional space by more than 41,000 asf to meet current enrollment demands and creates 9,973 asf of lecture, 45,504 asf of lab, 6,928 asf office 321 asf technology and 3,315 asf of other space types.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 10/12/2007 8/29/2007
Preliminary Planning Approved, Design Begins 3/14/2008 3/14/2008
Design Approved, Authorized to go to Bid 12/1/2009 12/14/2009
Construction Begins 4/15/2010 4/21/2010
Facility Enters Into Use 7/16/2012 10/8/2012
Project Closeout
Project Budget Summary
State Financing $27,581,000
Local/Non-State Financing $27,072,734
Total Financing $54,653,734
State Contact Cheryl Larry
clarry@cccco.edu
District Contact Doug Jensen
6617226302
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $1,194,000 $410,000 $1,604,000
Working Drawings $1,576,000 $702,226 $2,278,226
Construction $23,095,000 $24,692,776 $47,787,776
Equipment $1,716,000 $1,267,732 $2,983,732
Total Project Financing $27,581,000 $27,072,734 $54,653,734
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $1,604,000 $0 $1,604,000
Working Drawings $2,128,000 $150,226 $2,278,226
Construction $47,364,000 $423,776 $47,787,776
Contract $44,862,000 $4,502,916 $40,359,084
Allowances $2,502,000 $4,926,692 $7,428,692
Equipment $1,716,000 $1,267,732 $2,983,732
Total Project Financing $52,812,000 $1,841,734 $54,653,734