California Community Colleges Proposition 1D Project Details
Project Name Theatre Arts Facility
CFIS 40.03.114
District ANTELOPE VALLEY COMMUNITY COLLEGE DISTRICT
College ANTELOPE VALLEY COLLEGE
City Lancaster
County Los Angeles
Senate District 17
Assembly District 36
Project Description and Status
Project Type Support Instruction
Date Funded 6/30/2006
Project Description The project creates a new building to increase educational opportunities for students to learn the skills associated with theater lighting, sound, costume design, and scene production as well as additional opportunities to practice and perform coordinated productions involving the combination of music, dancing, and acting. The building was redesigned slightly while creating the construction documents to improve traffic and pedestrian safety in the area. The revised project constructs a 19,536 square foot building with 718 square feet (sf) of office space and 18,818 sf of other space including 17,511 sf for the theater arts program.
Project Status Construction Complete
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 1/1/2007 11/14/2006
Preliminary Planning Approved, Design Begins 6/1/2007 6/8/2007
Design Approved, Authorized to go to Bid 9/15/2008 6/17/2008
Construction Begins 10/21/2008 12/8/2008
Facility Enters Into Use 5/11/2011 6/13/2011
Project Closeout
Project Budget Summary
State Financing $11,276,000
Local/Non-State Financing $14,734,000
Total Financing $26,010,000
State Contact Cheryl Larry
clarry@cccco.edu
District Contact Doug Jensen
6617226302
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $382,000 $443,000 $825,000
Working Drawings $490,000 $761,000 $1,251,000
Construction $9,756,000 $12,498,000 $22,254,000
Equipment $648,000 $1,032,000 $1,680,000
Total Project Financing $11,276,000 $14,734,000 $26,010,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $597,000 $228,000 $825,000
Working Drawings $766,000 $485,000 $1,251,000
Construction $15,244,000 $7,010,000 $22,254,000
Contract $14,360,000 $6,741,000 $21,101,000
Allowances $884,000 $269,000 $1,153,000
Equipment $1,012,000 $668,000 $1,680,000
Total Project Financing $17,619,000 $8,391,000 $26,010,000