California Community Colleges Proposition 1D Project Details
Project Name One-Stop Student Services Center
CFIS 40.02.118
District ALLAN HANCOCK COMMUNITY COLLEGE DISTRICT
College ALLAN HANCOCK COLLEGE
City Santa Maria
County Santa Barbara
Senate District 15
Assembly District 33
Project Description and Status
Project Type Modernize Institution
Date Funded 6/30/2006
Project Description The project constructs a 25,188 square foot One-Stop Student Services Center. The project creates 720 square feet (sf) of lecture space, 900 sf of laboratory space, 18,349 sf of office space, 1,749 sf of library space, and 3,470 sf of other space. The new center will replace aged and deteriorating nine buildings designated on campus as buildings A, B, I, N annex, U, X, V, T, and S2. These nine buildings will be demolished as part of the project.
Project Status Under Construction
Project Schedule Detail
Scheduled Actual
Preliminary Planning Begins 9/17/2007 11/14/2006
Preliminary Planning Approved, Design Begins 2/18/2008 12/14/2007
Design Approved, Authorized to go to Bid 6/22/2009 6/24/2009
Construction Begins 2/1/2010 2/25/2010
Facility Enters Into Use 3/14/2014
Project Closeout
Project Budget Summary
State Financing $16,557,000
Local/Non-State Financing $12,965,000
Total Financing $29,522,000
State Contact Eric Thorson
ethorson@cccco.edu
District Contact Felix Hernandez Jr., Vice Pres
8059226966
Project Financing Detail
State Local Total
Acquisition $0 $0 $0
Preliminary Plans $629,000 $319,000 $948,000
Working Drawings $837,000 $970,000 $1,807,000
Construction $15,020,000 $10,976,000 $25,996,000
Equipment $71,000 $700,000 $771,000
Total Project Financing $16,557,000 $12,965,000 $29,522,000
Project Cost Detail
Initial Budget Variance Revised Budget
Acquisition $0 $0 $0
Preliminary Plans $629,000 $319,000 $948,000
Working Drawings $837,000 $970,000 $1,807,000
Construction $15,020,000 $11,294,000 $26,314,000
Contract $14,166,000 $9,450,000 $23,616,000
Allowances $854,000 $1,844,000 $2,698,000
Equipment $71,000 $8,703 $79,703
Total Project Financing $16,557,000 $12,591,703 $29,148,703